Friday, December 28, 2012

Building on QB Wings

The quickbuilt wings are already fairly complete. The key remaining tasks include: wiring the wings, adding the lights, Autopilot servo and pitot-tube, Plumbing pitot tube line, mounting the ailerons and flaps and finally riveting one of the skin on the wings.
 
The progress on the wings have been slow. While the primary focus has been the fuselage so far, few of the things have been accomplished in past few months.
 
First, mounting the heated pitot was tackled. This is dynon heated pitot with a mount that was bought from SafeAir (5 hrs). The wiring and the plumbing is also done.The mount still needs to be riveted to the bottom of the wing:
 





 
 
 


 
The AP roll-servo is installed on the right wing (2hrs). One of the aileron pushrods was already fabricated by the previous builder. So it was first simply measured to verify the length:
 
 
One of the dreaded task in mounting the landing and taxi lights on the wings is the cutting out portions of perfectly good wings. Glenn, who is an artist in metal work, did those effortlessly. Taxi and landing lights are installed in left and right wings respectively (10 hrs).

 
 
I also decided to put in flop-tube in the left wing. Did not realize that this would take long. Thanks to Glenn, the flop tube and the fuel sender in the left wing was done (8 hrs).
 
 
 

Meanwhile, the wingtips are also being fitted. Aligning the edges of the wingtips, aileron and the flaps is important and the progress is slow and incremental (5 hrs):


 
 
The previous builder had mounted the aileron and flaps for left wing already. But the right wing needs to be taken care off (5 hrs):
 



The work on the wing will continue in parallel to the fuselage.