Saturday, November 30, 2013

Baffles and Ignition Cable Routing

I have asking significant help from Glenn and Dennis on the firewall forward. Their experience makes me much more comfortable dealing with this complex part of the build.
 
Over the past few weeks, we have been working tirelessly on the baffles (> 20 hrs). I have ECI cylinders that have slightly different shape than the baffle kit that Vans provides. Consequently, we had to modify things here and there. Mostly, the baffles did fit initially, but with any sheet metal work, there is cutting, deburring etc. no matter what. Decided to paint then red:
 

 
 
Here is snapshot with final baffles installations. Glenn and others have made many baffles in the past, so it was a non-event. It would have taken me a long time to get through this without their help.


Close up shots of the oil cooler mount and the inverted system. The engine compartment is beginning to look somewhat complete. Still lots of wiring to finalize.
 

Monday, September 30, 2013

Quick Drain Plug

Spent quite a bit of time head scratching about quick drain oil plug. Basically, I got a superior oil sump and with the inverted oil system, we needed to make some decisions about how to route the oil line and install the quick drain plug.
 
Here is what we started with. As you can see the exhaust lines are in the way and make the installation hard:
 
 
This is what we finally did. Re-routed the inverted oil line to the sump below the exhaust lines and in the center goes the oil drain plug (5 hrs).


Friday, August 30, 2013

Cowling and installing RAM air

Fiberglass work is never ending on cowling. Have been fitting trimming for a while and finally got it to sit the way we liked a few weeks back.
 
I decided to go the RAM air route instead of the traditional Van's snorkel. Two main reasons for this: first, it just fits, no fiberglass work like the traditional snorkel. Second, there is a good chance that it'll give us some boost in HP (especially at altitude with RAM air open).
 
Had to  modify the cowl a bit for the RAM air to work (10 hrs):
 
 
Here is the final fitted cowl. Took us too long to do this part (> 25 hrs)...

 
Also decided to go the hinge-less oil door route. Not too complex but just a little different than the stock solution (5 hrs):


Thursday, August 15, 2013

Propeller arival and intial mounting

The prop is here! This i the last big purchase of the build (hopefully!). I got a whirlwind 200RV prop and it appears that this prop is suitable on nose heavy RV-8s due to its light weight.
 
 
Again , thanks to Glenn's previous experiences as a builder, mounting the propeller was not a big deal. The good thing about the whirlwind prop is that it comes with the spinner (unlike other props, where you have to build the spinner).


Tuesday, July 30, 2013

Canopy initial fit

Since the top skin is now riveted, we can start thinking about the canopy as well. It seems that many of the builders find the canopy the most challenging aspect of the build. I have doing a bunch of reading about it and it looks like we can divide the canopy build process into three steps: 1) Fitting the plexi bubble and making the big cut. 2) Attaching the plexi-bubble to the frame 3) Fiberglass (canopy skirts and windscreen fairings).
 
Currently, we just are tacking #1. That is fit the canopy and then make the big cut that separated aft section from the windscreen. It took a bunch of fitting / trimming / sanding and took probably good 10-15 hrs just to get the right fit.
 
 
 
The big cut itself was not a big deal (nervous of course, but once you get started you get it done pretty fast):

 
 
Here is the picture of drill and temporarily bolted wind screen.

 
I also started fiddling with the tail fairings etc. I am hoping that we can wrap up the tail section pretty soon. Here is the trial fit for the fairing. It took a bunch of trimming and sanding to get to this stage (2 hrs).


Friday, June 28, 2013

Riveting the front turtle deck

Since the panel is mostly in, we decided to go ahead and rivet the front turtle deck. There were a bunch of things that needed to be taken care off before actually riveting the skin. First, we got the cowl hinges aligned and positioned. That took a bunch of time. I spent a bunch of time fitting the skin, drilling and de-burring all the holes (5 hrs)!
 
Here is the shiny clecoed skin:

 
 
Another shot! The skin on makes the build pretty exciting now. With this riveted on a majority of the airframe work is done:
 

 
We pretty much spent the entire day riveting. Some rivets were hand squeezed, while a majority of them were driven.

 
I had to lay down head first in the fuselage to get some bucking access. Not very fun due to the tight spaces. I am glad its over! Here is the snapshot of how we did it!


Almost done! The skin is shiny! It was well worth our more than 8 hours of hard work!
 


Wednesday, May 15, 2013

Oil lines and inverted system

Next, we move to the firewall foreword section. I got to say this is probably the most intimidating part of the build for me as I am completely novice in this space. Electrical stuff I can deal with but engine... never had to fiddle with ever.
 
Anyway, here it goes. Started with mounting the inverted oil components on the firewall and the engine mount. Well that was the easy part. The difficult part was getting the right hoses. I decided to get the hose pre-made from TS Flightlines. He first shipped is a bunch of hoses that we cut to the size we wanted. The hoses were shipped back. Tom at TS Flightlines then put fire sleeves and connects and we ended up high quality hoses that fit perfectly.
 
 
 
Also ended up routing the control cables for throttle, mixture and prop. Still figuring out the routing for EGT/CHT probes plus other electrical stuff.

 
 
This part of the built took pretty long (much longer than I anticipated). I think we spent more than 50 hrs just figuring stuff (trying and retrying). The attention to detail needs to quite a bit and that takes a lot of time.

Monday, April 15, 2013

Interior paint and riveting the floor boards

Both Glenn and Dennis are gone for a few weeks now. I am pretty much by myself in the shop and have started tackling a bunch of small stuff that needs to be taken care off.
 
 
First, I need to paint the interior. Instead of spraying the paint directly on the interior, I decided to pull out all the panels, floorboards seats etc. and painted them on the bench. I used the Hammered gray paint from Rustoleum. It looks pretty good for a novice painter like me. Prepping took a lot of time. All in all, I probably spent 20 hrs or so prepping / painting / uninstalling / reinstalling.
 
 
Once the floorboards were painted and dried. I decided to go ahead and rivet them. The plans make it fairly complex to move forward unless the floorboards are in place. For example, the flap rod and motor cannot be installed before the boards are in place. Pop-riveting the board was fun and it took me a little over 5 hrs to get everything in place.

 
Also decided to mount the two GPS antennas (Garmin and Dynon) in the firewall forward section. I simply ordered RV-12 antenna mounts and pop riveted them (3 hrs):



Finally, decided to replace the standard Van's tailwheel with a bell fork and a DJM lightweight tailwheel. There was some confusion about what spacers I needed to use but we sorted it out in a couple of mail exchanges (2 hrs):



Friday, March 8, 2013

Mounting the engine



Big week! Vinayak, my son was born. Ashima does not want me to post his pictures so ... Coincidentally, the engine also arrived. I am taking it as a good sign!

Here is the engine fresh of the truck and crate. Neatly wrapped by the Aerosport folks! 

 
Glenn was at it right away and quickly mounted the engine before end of the day. Amazing how an experienced helper can do the big things, such as mounting an engine so easily. If it were by myself I would have procrastinated and worried on and on.


 
Here are the obligatory photos after the engine was mounted:



It is beginning to look like an Airplane!